GAA 2019 OO-119B00044

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: SIFFU BRIDGE (B01157LZ) ALONG SANTIAGO-TUGUEGARAO ROAD, ROXAS, ISABELA

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: SIFFU BRIDGE (B01157LZ) ALONG SANTIAGO-TUGUEGARAO ROAD, ROXAS, ISABELA is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱542,395,314.30. Status: Past target date (DPWH On-Going). Contractor on record: ADVANCED FOUNDATION CONST SYSTEMS CORP. Figures trace to dpwh.

Region II, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

39 projects · ₱5.6B total · 0 flags

4. Implementation

Contract Amount

₱542,395,314.30

Progress

Past target date (DPWH On-Going)

Start Date

August 28, 2019

Target End

June 7, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.