Roads16G00170

KALIBO CIRCUMFERENTIAL ROAD FROM CALANGCANG TO MINA INCLUDING BRIDGE (KALIBO BRIDGE III), AKLAN LONE

KALIBO CIRCUMFERENTIAL ROAD FROM CALANGCANG TO MINA INCLUDING BRIDGE (KALIBO BRIDGE III), AKLAN LONE is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱234,000,297.56. Status: Reported complete (DPWH). Contractor on record: ADVANCED FOUNDATION CONST SYSTEMS CORP. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

39 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: WIDENING OF PERMANENT BRIDGES: NAGUILIAN BRIDGE ALONG DAANG MAHARLIKA (LZ)(PARALLEL BRIDGE)

Region II, Region II

2020₱969.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: REPLACEMENT OF PERMANENT WEAK BRIDGES: SIFFU BRIDGE (B01157LZ) ALONG SANTIAGO-TUGUEGARAO ROAD, ROXAS, ISABELA

Region II, Region II

2019₱542.4M
Past target date (DPWH On-Going)
No sat.

LOCALLY FUNDED PROJECTS: ONSTRUCTION/ REHAB./ IMPV'T OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, ROADS AND BRIDGES- LOCAL BRIDGES: CONST'N OF PIGALO BRIDGE & APPROACHES ALONG ALICIA-ANGADANAN-SAN GUILLERMO PROVINCIAL ROAD, ANGADANAN, ISABELA

Region II, Region II

2016₱437.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM: WIDENING OF PERMANENT BRIDGES: MINANGA BRIDGE (B01129LZ) ALONG DAANG MAHARLIKA (LZ) (PARALLEL BRIDGE), TUMAUINI, ISABELA

Region II, Region II

2020₱374.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM :CONSTRUCTION OF MISSING LINKS/NEW ROADS: JCT. CAGAYAN VALLEY ROAD-SAMPAGUITA-WARAT-LA SUERTE-CATARAUAN-AFUSING ROAD (AMULUNG BRIDGE AND APPROACHES), CAGAYAN

Region II, Region II

2022₱347.2M
Reported complete (DPWH)

WIDENING OF BRIDGE - SIBALOM BR. (B00123PN) ALONG ILOILO - ANTIQUE RD

Region VI, Region VI

2019₱259.4M
Reported complete (DPWH)
View all 39 projects →

4. Implementation

Contract Amount

₱234,000,297.56

Progress

Reported complete (DPWH)

Start Date

November 9, 2016

Target End

December 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.