Roads17E00029

CONST/IMPRVT OF ACCESS ROAD OF GUADALUPE-SAN NICOLAS-DECABOBO LEADING TO BORAC RORO PORT STA.16+820-STA.18+044; STA.24+918.40-STA.25+528.58, CORON, PALAWAN

CONST/IMPRVT OF ACCESS ROAD OF GUADALUPE-SAN NICOLAS-DECABOBO LEADING TO BORAC RORO PORT STA.16+820-STA.18+044; STA.24+918.40-STA.25+528.58, CORON, PALAWAN is a DPWH-tracked public work in Palawan 1st DEO, Region IV-B. Reported contract value: ₱86,756,701.84. Status: Reported complete (DPWH). Contractor on record: ONE HUNDRED PERCENT CONST AND DEVELOPMENT CORP FORMERLY:BCT TRADING. Figures trace to dpwh.

Palawan 1st DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Dipuyai Bridge, Coron-Busuanga Road, Palawan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0024381

₱832,166.00 · FY2017

Released to 00000 - Supreme Court of To cover he Philippines and the Lower indi ourts (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

133 projects · ₱5.7B total · 0 flags

4. Implementation

Contract Amount

₱86,756,701.84

Progress

Reported complete (DPWH)

Start Date

May 21, 2017

Target End

March 16, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.