Buildings and Facilities19EA0032

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. TAYTAY, STA. CRUZ, MARINDUQUE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. TAYTAY, STA. CRUZ, MARINDUQUE is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱4,898,376.52. Status: Reported complete (DPWH). Contractor on record: TRI-DAN-J CONST AND TRADING. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0000617

₱11,074,000.00 · FY2019

Released to Revenue Regional Office X - Legaspi Cit (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,898,376.52

Progress

Reported complete (DPWH)

Start Date

July 12, 2019

Target End

November 8, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.