Roads18EB0014

NETWORK DEV'T. - CONST. OF BY-PASS AND DIVERSION RDS., ABRA DE ILOG BYPASS RD, INCL. ROW, OCC. MINDORO, STA. 0+732 - STA. 2+232, ABRA DE ILOG, OCC. MINDORO

NETWORK DEV'T. - CONST. OF BY-PASS AND DIVERSION RDS., ABRA DE ILOG BYPASS RD, INCL. ROW, OCC. MINDORO, STA. 0+732 - STA. 2+232, ABRA DE ILOG, OCC. MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱73,396,947.93. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bank Protection and Rechanneling, Barangay Alacaak, Sta. Cruz, Occidental Mindoro
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Mindoro Occidental DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

466 projects · ₱13.0B total · 1 flags

Other projects by this contractor

View all 466 projects →

4. Implementation

Contract Amount

₱73,396,947.93

Progress

Reported complete (DPWH)

Start Date

August 19, 2021

Target End

February 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.