GAA 2025 SSP25OC0054

CONSTRUCTION OF DRAINAGE MAIN ALONG ESTRELLA STREET FROM EDSA TOWARDS PASIG RIVER, BARANGAY GUADALUPE VIEJO,MAKATI CITY, METRO MANILA

CONSTRUCTION OF DRAINAGE MAIN ALONG ESTRELLA STREET FROM EDSA TOWARDS PASIG RIVER, BARANGAY GUADALUPE VIEJO,MAKATI CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱48,510,000.00. Status: Past target date (DPWH On-Going). Contractor on record: TWO DIMENSION CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Don Galo River, Barangay Don Galo, Parañaque City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

98 projects · ₱2.0B total · 3 flags

Other projects by this contractor

View all 98 projects →

4. Implementation

Contract Amount

₱48,510,000.00

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2025

Target End

November 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.