GAA 2025 OO-125HB0008

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD, K0177+398 - K0178+477, K0184+296 - K0185+157

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS- THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD, K0177+398 - K0178+477, K0184+296 - K0185+157 is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱126,225,622.09. Status: Past target date (DPWH On-Going). Contractor on record: NEWINGTON BUILDERS INC FOR: E GARDIOLA CONSTRUC. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Dike, Cahayag CIS, Tubigon, Bohol
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bohol 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

189 projects · ₱20.4B total · 0 flags

4. Implementation

Contract Amount

₱126,225,622.09

Progress

Past target date (DPWH On-Going)

Start Date

July 14, 2025

Target End

January 12, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.