CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER @ CAMP FRANCISCO DAGOHOY), BARANGAY POBLACION III, TAGBILARAN CITY, BOHOL

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER @ CAMP FRANCISCO DAGOHOY), BARANGAY POBLACION III, TAGBILARAN CITY, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱4,158,000.00. Status: Reported complete (DPWH). Contractor on record: JRV CONST AND SUPPLY. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱1,500 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21HA0070 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-05-21 → 2021-07-29

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER @ CAMP FRANCISCO DAGOHOY), BARANGAY POBLACION III, TAGBILARAN CITY, BOHOL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱1,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Candumayao Flood Control, Catigbian, Bohol
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Bohol 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

38 projects · ₱373.2M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, CANSAGA BAY BR. (B00613CB) ALONG CANSAGA BAY BRIDGE

Region VII, Region VII

2021₱144.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM, POBLACION,

Bohol 3rd DEO, Region VII

2021₱28.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - DRAINAGE PROTECTION WORKS - CONSTRUCTION OF DIKE AT SITIO SUN OK, LUNGSODAAN, CANDIJAY, BOHOL STA. 0+000 - STA. 0+177.50

Bohol 3rd DEO, Region VII

2021₱19.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - ARCHBISHOP REYES FLYOVER 1(B00043CB) ALONG ARCHBISHOP REYES AVE., CEBU CITY

Cebu City DEO, Region VII

2021₱15.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM - REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES, TOHOGON BRIDGE (B00114BH) ALONG JCT. (LIR) CARMEN-SAGBAYAN-BACANI ROAD, K0164+251

Bohol 3rd DEO, Region VII

2021₱14.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM -LOCAL INFRASTRUCTURE PROGRAM - FLOOD CONTROL AND DRAINAGE - FLOOD CONTROL STRUCTURES/FACILITIES - CONSTRUCTION OF RIVERSIDE FLOOD CONTROL STRUCTURE, BARANGAY CANAWA, CANDIJAY, BOHOL STA. 0+317.00 - STA. 0+496.50 (RIGHT SIDE)

Bohol 3rd DEO, Region VII

2021₱14.3M
Reported complete (DPWH)
View all 38 projects →

4. Implementation

Contract Amount

₱4,158,000.00

Progress

Reported complete (DPWH)

Start Date

March 15, 2021

Target End

July 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)BoholCity of TagbilaranPoblacion III
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.