Flood Control and Drainage19EF0125

CONSTRUCTION CULASIAN FLOOD CONTROL, BRGY, CULASIAN, RIZAL, PALAWAN

CONSTRUCTION CULASIAN FLOOD CONTROL, BRGY, CULASIAN, RIZAL, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱4,852,381.85. Status: Reported complete (DPWH). Contractor on record: RAK TRADING AND CONST 42613. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,852,381.85

Progress

Reported complete (DPWH)

Start Date

August 22, 2019

Target End

January 28, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.