Bridges17AA0158

WIDENING OF PERM BRIDGES TO MPORE THAN 2 LANES -LANA BR.(B00771LZ) ALONG LAOAG-SAART-PIDDIG SOLSONA

WIDENING OF PERM BRIDGES TO MPORE THAN 2 LANES -LANA BR.(B00771LZ) ALONG LAOAG-SAART-PIDDIG SOLSONA is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱9,799,360.30. Status: Reported complete (DPWH). Contractor on record: KATHA BUILDERS & SUPPLIES INC. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱45,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0017541 · ₱1,955,200 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17AA0158 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-01-04 → 2025-10-09

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: WIDENING OF PERM BRIDGES TO MPORE THAN 2 LANES -LANA BR.(B00771LZ) ALONG LAOAG-SAART-PIDDIG SOLSONA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bislak River, Brgy. Dagupan, Vintar, Ilocos Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0017541

₱1,955,200.00 · FY2017

Released to Regional Office - VI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

74 projects · ₱6.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN), PAOAY-LAOAG INTERNATIONAL AIRPORT ACCESS ROAD, LAOAG CITY, ILOCOS NORTE

Region I, Region I

2025₱198.6M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG QUIAOIT RIVER (CONSTRUCTION OF DIVERSION CHANNEL), BATAC, ILOCOS NORTE (PACKAGE B)

Region I, Region I

2024₱198.0M
Past target date (DPWH On-Going)

LOCAL PROGRAM, FLOOD CONTROL AND DRAINAGE, DRAINAGE / PROTECTION WORKS, CONSTRUCTION/REHABILITATION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG JCT. MSR OLD ZIGZAG RD, QUEZON

Quezon 4th DEO, Region IV-A

2021₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (LAOAG CITY-BACARRA SECTION), ILOCOS NORTE (PACKAGE B)

Region I, Region I

2024₱193.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF PUERTO PRINCESA EAST COASTAL ROAD, PUERTO PRINCESA CITY, PALAWAN

Region IV-B, Region IV-B

2023₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS, TANGAOAN - PALLAS ROAD LEADING TO PARAISO ECOTOURISM PROJECT ECO AND REFORESTATION PROJECT, PIDDIG, ILOCOS NORTE

Region I, Region I

2016₱181.3M
Reported complete (DPWH)
View all 74 projects →

4. Implementation

Contract Amount

₱9,799,360.30

Progress

Reported complete (DPWH)

Start Date

May 13, 2017

Target End

April 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)Ilocos NortePiddigArua-ay
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.