Flood Control and Drainage24A00288

BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG QUIAOIT RIVER (CONSTRUCTION OF DIVERSION CHANNEL), BATAC, ILOCOS NORTE (PACKAGE B)

BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG QUIAOIT RIVER (CONSTRUCTION OF DIVERSION CHANNEL), BATAC, ILOCOS NORTE (PACKAGE B) is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱197,998,739.08. Status: Past target date (DPWH On-Going). Contractor on record: KATHA BUILDERS & SUPPLIES INC. Figures trace to dpwh.

Region I, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

74 projects · ₱6.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN), PAOAY-LAOAG INTERNATIONAL AIRPORT ACCESS ROAD, LAOAG CITY, ILOCOS NORTE

Region I, Region I

2025₱198.6M
Past target date (DPWH On-Going)

LOCAL PROGRAM, FLOOD CONTROL AND DRAINAGE, DRAINAGE / PROTECTION WORKS, CONSTRUCTION/REHABILITATION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG JCT. MSR OLD ZIGZAG RD, QUEZON

Quezon 4th DEO, Region IV-A

2021₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (LAOAG CITY-BACARRA SECTION), ILOCOS NORTE (PACKAGE B)

Region I, Region I

2024₱193.0M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF PUERTO PRINCESA EAST COASTAL ROAD, PUERTO PRINCESA CITY, PALAWAN

Region IV-B, Region IV-B

2023₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS, TANGAOAN - PALLAS ROAD LEADING TO PARAISO ECOTOURISM PROJECT ECO AND REFORESTATION PROJECT, PIDDIG, ILOCOS NORTE

Region I, Region I

2016₱181.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION (COMPLETION) OF LANGIDEN BRIDGE, SUYO AND NALNAS - DALAYAP, LANGIDEN AND PIDIGAN, ABRA

Cordillera Administrative Region, Cordillera Administrative Region

2023₱178.5M
Reported complete (100% progress, DPWH status On-Going)
View all 74 projects →

4. Implementation

Contract Amount

₱197,998,739.08

Progress

Past target date (DPWH On-Going)

Start Date

April 8, 2024

Target End

April 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.