GAA 2025 SSP25HN0106

SSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF NANGKA-TUGBONGGAN ROAD WITH SLOPE PROTECTION SYSTEM (PACKAGE 1), CONSOLACION, CEBU

SSP: SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF NANGKA-TUGBONGGAN ROAD WITH SLOPE PROTECTION SYSTEM (PACKAGE 1), CONSOLACION, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱48,979,733.47. Status: Past target date (DPWH On-Going). Contractor on record: KYLE CONST SERVICES. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cansaga River, Barangay Tilhaong, Consolacion, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 6th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱297.6M total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MANANGA RIVER, PACKA

Cebu City DEO, Region VII

2025₱96.0M
Past target date (DPWH On-Going)
No sat.

CSSP: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - CENTENNIAL AVENUE LEADING TO CORDOVA RORO PORT, CORDOVA, CEBU

Cebu 6th DEO, Region VII

2024₱29.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - CEBU NORTH HAGNAYA WHARF ROAD - K0008+(-703) - K0008+(-42), MANDAUE CITY

Cebu 6th DEO, Region VII

2020₱15.8M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure along Pitogo River, Phase III, Consolacion, Cebu

CONSOLACION (CEBU), CEBU, Region VII

2023₱14.7M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS-CEBU-BALAMBAN TRANSCENTRAL HIGHWAY - K0026+834 - K0026+879, CEBU CITY

Cebu City DEO, Region VII

2024₱12.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

LP: LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL BRIDGES - CONSTRUCTION OF BRIDGE AT LAMAC, CONSOLACION, CEBU

Cebu 6th DEO, Region VII

2019₱11.3M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱48,979,733.47

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

July 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.