Buildings and Facilities24PE0077

CONSTRUCTION OF 3-STOREY 13-CLASSROOM SCHOOL BUILDING WITH SCIENCE LABORATORY ROOM IN AMBANGEG NATIONAL HIGH SCHOOL, BARANGAY DAKLAN, BOKOD, BENGUET

CONSTRUCTION OF 3-STOREY 13-CLASSROOM SCHOOL BUILDING WITH SCIENCE LABORATORY ROOM IN AMBANGEG NATIONAL HIGH SCHOOL, BARANGAY DAKLAN, BOKOD, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱39,797,801.54. Status: Past target date (DPWH On-Going). Contractor on record: SEJ CONST & AGGREGATES. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ampeg - ok CIS Flood Control along Alanod Creek, Kabayan, Benguet
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Benguet 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱39,797,801.54

Progress

Past target date (DPWH On-Going)

Start Date

August 27, 2024

Target End

July 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.