Roads22P00040

CONSTRUCTION OF ROAD, ANOVANG DOMOLPOS ITOGON - KAYAPA, NUEVA VIZCAYA, ITOGON BENGUETANOVANG, DOMOLPOS, ITOGON, BENGUET

CONSTRUCTION OF ROAD, ANOVANG DOMOLPOS ITOGON - KAYAPA, NUEVA VIZCAYA, ITOGON BENGUETANOVANG, DOMOLPOS, ITOGON, BENGUET is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱297,000,000.00. Status: Reported complete (DPWH). Contractor on record: SEJ CONST & AGGREGATES. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱297,000,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

December 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.