Roads23DM0064

CONSTRUCTION OF ACCESS ROAD, BAGONG SILANG - VILLA BATABAT - SAN VICENTE, BUENAVISTA, QUEZON

CONSTRUCTION OF ACCESS ROAD, BAGONG SILANG - VILLA BATABAT - SAN VICENTE, BUENAVISTA, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: DQT BUILDERS CORP FORMERLY DQT BUILDERS. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Agdangan River, Agdangan, Quezon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Quezon 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

191 projects · ₱5.8B total · 0 flags

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

March 30, 2023

Target End

August 26, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.