Roads20IF0015

PREVENTIVE MAINTENANCE - PRIMARY ROADS, ORMOC - BAYBAY SO. LEYTE BDRY. ROAD, K1017+840-K1018+334, K1018+459.05-K1019+422, K1019+429-K1020+042, K1020+125.09-K1021+484, K1021+535-K1021+892, K1021+911-K1022+373, K1022+411-K1022+992

PREVENTIVE MAINTENANCE - PRIMARY ROADS, ORMOC - BAYBAY SO. LEYTE BDRY. ROAD, K1017+840-K1018+334, K1018+459.05-K1019+422, K1019+429-K1020+042, K1020+125.09-K1021+484, K1021+535-K1021+892, K1021+911-K1022+373, K1022+411-K1022+992 is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱91,674,540.73. Status: Reported complete (DPWH). Contractor on record: OCTAGON CONCRETE SOLUTIONS INC. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱39,212,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bao Flood Control (Upstream Ormoc Side), Kananga, Leyte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Leyte 4th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

69 projects · ₱6.7B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM (LP) - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF TACLOBAN AIRPORT PASSENGER TERMINAL BUILDING PHASE 3, TACLOBAN CITY

Region VIII, Region VIII

2024₱964.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONST. OF AIRPORT FACILITY, BUSUANGA AIRPORT, CORON, PALAWAN

Region IV-B, Region IV-B

2024₱400.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS./S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF R0AD, BRGY. LIYANG, PILAR TO BRGY. BILOLO, ORION, BATAAN (PACKAGE 1)

Region III, Region III

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE K0115+949 TO K0118+000, ROXAS, PALAWAN

Region IV-B, Region IV-B

2018₱162.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (UPSTREAM LEFTSIDE), ABORLAN, PALAWAN

Region IV-B, Region IV-B

2024₱154.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (UPSTREAM RIGHTIDE), ABORLAN, PALAWAN

Region IV-B, Region IV-B

2024₱147.1M
Past target date (DPWH On-Going)
View all 69 projects →

4. Implementation

Contract Amount

₱91,674,540.73

Progress

Reported complete (DPWH)

Start Date

December 1, 2020

Target End

April 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.