Buildings and Facilities18PL0155

CONSTRUCTION OF ONE(1) STOREY - EIGHT(8) UNIT WORKSHOP SCHOOL WITH ATTACHED CR, TANUDAN VOCATIONAL SCHOOL, TANUDAN, KALINGA

CONSTRUCTION OF ONE(1) STOREY - EIGHT(8) UNIT WORKSHOP SCHOOL WITH ATTACHED CR, TANUDAN VOCATIONAL SCHOOL, TANUDAN, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱35,122,171.41. Status: Reported complete (DPWH). Contractor on record: MGSR CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Angalipan Flood Control, Cudal, Tabuk City, Kalinga
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIX-18-0023791

₱80,000.00 · FY2018

Released to Al Tambulig (Echanca) National High au School Ma To (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

48 projects · ₱549.6M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - MANUEL S. AGYAO BOULEVARD - K0507 + 360-K0510 + 075

Lower Kalinga DEO, Cordillera Administrative Region

2024₱63.7M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS ALONG KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION), K0496+-593 - K0496+-027, K0496+523-K0497+134, K0513+800-K0514+549

Lower Kalinga DEO, Cordillera Administrative Region

2020₱62.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM -CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-PRIMARY ROADS - KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION) - K0500+474 - K0501+753

Lower Kalinga DEO, Cordillera Administrative Region

2023₱62.2M
Reported complete (100% progress, DPWH status On-Going)
No sat.

LOCAL PROGRAM (LP) - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF DPWH LOWER KALINGA DEO BUILDING, TABUK, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱49.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF 3STY15CL, MACUTAY PALAO NATIONAL HIGH SCHOOL, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱48.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFETY AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS - KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION) - K0520+026 - K0521+000, K0524+128 - K0525+096

Lower Kalinga DEO, Cordillera Administrative Region

2022₱46.7M
Reported complete (DPWH)
View all 48 projects →

4. Implementation

Contract Amount

₱35,122,171.41

Progress

Reported complete (DPWH)

Start Date

June 22, 2018

Target End

March 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.