Roads24MF0004

KIDAPAWAN-ALLAH JUNCTION RD - K1679 +359 - K1680 + 105, K1680 + 152 - K1680 + 349

KIDAPAWAN-ALLAH JUNCTION RD - K1679 +359 - K1680 + 105, K1680 + 152 - K1680 + 349 is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱25,324,817.09. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ROBETH CONST AND DEV'T CORP FORMERLY: ROBETH GEN MDSE CONST. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Banga River ( Sampao Section ) , Isulan, Sultan Kudarat
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Sultan Kudarat 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

159 projects · ₱1.7B total · 0 flags

4. Implementation

Contract Amount

₱25,324,817.09

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 27, 2024

Target End

October 30, 2024

5. Audit