Buildings and Facilities25HD0083

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LINDOGON, SIBONGA, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LINDOGON, SIBONGA, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱1,974,405.13. Status: Past target date (DPWH On-Going). Contractor on record: CARCEL CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25HD0083 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    46% reported · imagery 2024-08-19 → 2025-01-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LINDOGON, SIBONGA, CEBU

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Valladolid River, Carcar City, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

41 projects · ₱198.8M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASEET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0011+(-591)-K0011+(-200), TALISAY CITY, CEBU

Cebu 1st DEO, Region VII

2023₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF J. FORTICH ST. - I. LIMKAKEN ST., CEBU CITY, CEBU

Cebu City DEO, Region VII

2025₱17.4M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/MAJOR REPAIR OF BRIDGE - CALAITAN BR. (B01229MN) ALONG NRJ BAYUGAN-CALAITAN-TANDAG RD, BAYUGAN, AGUSAN DEL SUR

Agusan del Sur 1st DEO, Region XIII

2024₱13.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - CEBU SOUTH COASTAL RD - K0015+(-295) - K0015+000, K0015+333 - K0015+500, TALIAY CITY, CEBU

Cebu 1st DEO, Region VII

2024₱11.6M
Reported complete (DPWH)
No sat.

REHABILITATION/MAJOR REPAIR OF BRIDGE - TUGPAN BR. (B00595MN) ALONG BUTUAN CITY-TALACOGON-LORETO-VERUELA-STA. JOSEFA RD, TALACOGON, AGUSAN DEL SUR

Agusan del Sur 1st DEO, Region XIII

2024₱9.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM -REHAB/RECONST/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - N BACALSO AVE (CEBU SOUTH RD) - K0041+707 - K0042+128, CARCAR CITY, CEBU

Cebu 1st DEO, Region VII

2024₱9.6M
Reported complete (DPWH)
View all 41 projects →

4. Implementation

Contract Amount

₱1,974,405.13

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2025

Target End

July 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)CebuSibongaLindogon
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.