GAA 2025 SSP25F00286

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE STRUCTURE, PACKAGE 1, DOWNSTREAM SEC

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF RIVER BANK PROTECTION WORKS AND DRAINAGE STRUCTURE, PACKAGE 1, DOWNSTREAM SEC is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱47,915,179.42. Status: Past target date (DPWH On-Going). Contractor on record: FIRST OMB CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

35 projects · ₱1.5B total · 0 flags

Other projects by this contractor

View all 35 projects →

4. Implementation

Contract Amount

₱47,915,179.42

Progress

Past target date (DPWH On-Going)

Start Date

July 9, 2025

Target End

January 24, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.