Water Provision and Storage23DD0335

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS, WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM IN TAYSAN, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS, WATER SUPPLY SYSTEM, CONSTRUCTION OF SOLAR WATER SYSTEM IN TAYSAN, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱9,507,276.84. Status: Reported complete (DPWH). Contractor on record: RANRAC CONST CORP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pinagsibaan Bridge 2, Rosario, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

47 projects · ₱336.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY STO. NIÑO, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱19.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING DRAINAGE STR

Batangas 4th DEO, Region IV-A

2025₱19.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD INCLUDING DRAINAGE AT

Batangas 4th DEO, Region IV-A

2025₱19.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY AGUILA, SAN JOSE, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BARANGAY BAWI FMR, BARANGAY BAWI, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱14.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF ROAD INCLUDING DRAINAGE AT BRGY. SAN ISIDRO, LIPA

Batangas 4th DEO, Region IV-A

2023₱14.4M
Reported complete (DPWH)
View all 47 projects →

4. Implementation

Contract Amount

₱9,507,276.84

Progress

Reported complete (DPWH)

Start Date

September 29, 2023

Target End

February 25, 2024

5. Audit