Roads25PC0006

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - AYAGA-STA. MARCELA-FLORA-LASAM RD- K0675 + 050 - K0677 + 000

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - AYAGA-STA. MARCELA-FLORA-LASAM RD- K0675 + 050 - K0677 + 000 is a DPWH-tracked public work in Apayao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱105,877,442.84. Status: Past target date (DPWH On-Going). Contractor on record: RODEKOM GEN CONST AND ENT. Figures trace to dpwh.

Apayao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Apayao-Abulug River Basin, Tanglagan Section, Sta. 163 + 101 - Sta. 163 + 551 (L/S) and Sta. 163 + 101- Sta. 163 + 601 (R/S), Calanasan, Apayao
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Apayao 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

80 projects · ₱6.4B total · 29 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF ROAD, KAPANGAN, BENGUET - SAN GABRIEL, LA UNIONKAPANGAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱197.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLI

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, ASIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), PACKAGE 1, BENGUETSABLAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱173.6M
Reported complete (DPWH)

Construction of Flood Control Structure along Baroro River, Barangay Bacsil, Bacnotan, LaUnion

BACNOTAN (LA UNION), LA UNION, Region I

2024₱154.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES/ DIVERSION ROADS INCLUDING ROW BAGUIO-LA TRINIDAD-ITOGON-SABLAN-TUBA-TUBLAY (BLISTT) OUTER RING CIRCUMFERENTIAL ROAD, INCL. ROW AND SLOPE PROTECTION, PHASE 3 (LABEY-LACAMEN SECTION, BOKOD, BENGUET), BENGUET LONE DISTRICT

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4A OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱144.8M
Reported complete (DPWH)
View all 80 projects →

4. Implementation

Contract Amount

₱105,877,442.84

Progress

Past target date (DPWH On-Going)

Start Date

March 12, 2025

Target End

February 4, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.