Construction of Revetment22DQ0091

Construction of Revetment along Bacoor River (tributary to Manila Bay), Phase 2, Bacoor City, Cavite

Construction of Revetment along Bacoor River (tributary to Manila Bay), Phase 2, Bacoor City, Cavite is a DPWH-tracked public work in BACOOR CITY (CAVITE), CAVITE, Region IV-A. Reported contract value: ₱98,999,931.03. Status: Reported complete (DPWH). Contractor on record: GRAIA CONST CORP. Figures trace to sumbong.

BACOOR CITY (CAVITE), CAVITE, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along River in Brgy. Palico 4, Imus City, Cavite
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cavite 3rd District Engineering Office · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

67 projects · ₱4.8B total · 23 flags

4. Implementation

Contract Amount

₱98,999,931.03

Progress

Reported complete (DPWH)

Start Date

April 7, 2022

Target End

April 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.