Roads23HA0050

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS - ACCESS ROAD LEADING TO MARIBOJOC PORT, MARIBOJOC, BOHOL

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS - ACCESS ROAD LEADING TO MARIBOJOC PORT, MARIBOJOC, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱38,800,000.00. Status: Reported complete (DPWH). Contractor on record: A A DE VERA CONST 6191. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Macaas Flood Control, Macaas, Tubigon, Bohol
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bohol 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱38,800,000.00

Progress

Reported complete (DPWH)

Start Date

May 3, 2023

Target End

February 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.