Buildings and Facilities20HC0092

REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LONOY ROMA, INABANGA, BOHOL

REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LONOY ROMA, INABANGA, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱969,000.00. Status: Reported complete (DPWH). Contractor on record: MAI CONST. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20HC0092 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-09-15 → 2017-09-15

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. LONOY ROMA, INABANGA, BOHOL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Abatan River, Brgy. Sto. Rosario, Antequera, Bohol
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bohol 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

169 projects · ₱806.4M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS - GUIHULNGAN - BALOC - ISABELA RD - K0117 + 825 - K0118 + 308, K0119 + 000- K0119 + 096, K0119 + 418 - K0119 + 650, K0126 + 029 - K01

Negros Oriental 1st DEO, Negros Island Region

2022₱26.5M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 1: CONSTRUCTION OF 2STY8CL SCHOOL BUILDING, DAGOHOY NATIONAL HIGH SCHOOL, DAGOHOY, BOHOL

Bohol 2nd DEO, Region VII

2023₱24.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 3)

Bohol 2nd DEO, Region VII

2024₱19.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF JCT. DUMAGUETE NORTH ROAD

Negros Oriental 1st DEO, Negros Island Region

2025₱14.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON ROAD GRAVEL STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) MABINAY - AYUNGON ROAD, AYUNGON, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱12.9M
Reported complete (DPWH)
No sat.

REHABILITATION (COMPLETION) OF DPWH BOHOL 2ND DEO INCLUDING OTHER FACILITIES, UBAY, BOHOL

Bohol 2nd DEO, Region VII

2023₱12.7M
Reported complete (DPWH)
View all 169 projects →

4. Implementation

Contract Amount

₱969,000.00

Progress

Reported complete (DPWH)

Start Date

March 9, 2020

Target End

May 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)BoholInabangaLonoy Roma
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.