Roads25FD0012

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG SIPOCOT-CABUSAO RD - K0394 + (-816) - K0410 + 243, SIPOCOT, CAMARINES SUR

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG SIPOCOT-CABUSAO RD - K0394 + (-816) - K0410 + 243, SIPOCOT, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 1st DEO, Region V. Reported contract value: ₱11,143,171.29. Status: Reported complete (DPWH). Contractor on record: MPIRE NINE CONST OPC. Figures trace to dpwh.

Camarines Sur 1st DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱11,143,171 · MPIRE NINE CONST OPC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-03-07 → 2021-03-07

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG SIPOCOT-CABUSAO RD - K0394 + (-816) - K0410 + 243, SIPOCOT, CAMARINES SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy Port Junction Norte, Ragay, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Sur 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Project

₱11,143,171.29 · MPIRE NINE CONST OPC

Award / contract ref: 25FD0012

Contractor

D

25 projects · ₱335.4M total · 0 flags

Other projects by this contractor

No sat.

OO1: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MILAOR-PILI BYPASS ROAD (PACKAGE 6), CAMARINES SUR

Camarines Sur 2nd DEO, Region V

2025₱29.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PAMPLONA-SAN FERNANDO BYPASS ROAD (PACKAGE 7), CAMARINES SUR

Camarines Sur 2nd DEO, Region V

2025₱29.1M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0406+912-K0407+000, K0407+216-K0407+500, LIBMANAN, CAMARINES SUR (2ND LEGSLATIVE DISTRICT)

Region V, Region V

2025₱21.6M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - NABUA-BALATAN RD - K0487 + 859 - K0487 + 945

Camarines Sur 5th DEO, Region V

2024₱19.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0478+537.11-K0478+861.00, BATO, CAMARINES SUR (5TH LEGISLATIVE DISTRICT)

Region V, Region V

2024₱18.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0429+183-K0429+250, K0429+264-K0429+385, K0429+404-K0429+440, K0429+450-K0429+495, K0429+516-K042

Region V, Region V

2024₱17.1M
Reported complete (100% progress, DPWH status On-Going)
View all 25 projects →

4. Implementation

Contract Amount

₱11,143,171.29

Progress

Reported complete (DPWH)

Start Date

February 17, 2025

Target End

May 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)Camarines SurCabusaoBiong
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.