Roads21OD0033

REHABILITATION OF ROADS AND DRAINAGE ALONG APOLONIA ST., (PHASE II), BRGY. MAPULANG LUPA, VALENZUELA CITY

REHABILITATION OF ROADS AND DRAINAGE ALONG APOLONIA ST., (PHASE II), BRGY. MAPULANG LUPA, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱9,571,909.69. Status: Reported complete (DPWH). Contractor on record: DJB CONST SERVICES 39576. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Rufina Francisco Compound (Phase 2), Barangay Mapulang Lupa, Valenzuela City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Metro Manila 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,571,909.69

Progress

Reported complete (DPWH)

Start Date

March 26, 2021

Target End

September 21, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.