Flood Control and Drainage24D00026

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, BARANGAY ILOG, INFANTA, QUEZON

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, BARANGAY ILOG, INFANTA, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱96,477,325.36. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: DJB CONST SERVICES. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱96,477,325.36

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 28, 2024

Target End

October 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.