Buildings and Facilities17DN0166No coordinates published by DPWH

CONSTRUCTION OF ONE (1) UNIT FOUR (4) STOREY, SIXTEEN (16) CLASSROOMS SCHOOL BUILDING, BAGONG PAGASA ELEMENTARY SCHOOL (SAN JUAN B. FLOODWAY ES), TAYTAY, RIZAL

CONSTRUCTION OF ONE (1) UNIT FOUR (4) STOREY, SIXTEEN (16) CLASSROOMS SCHOOL BUILDING, BAGONG PAGASA ELEMENTARY SCHOOL (SAN JUAN B. FLOODWAY ES), TAYTAY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱44,773,435.20. Status: Reported complete (DPWH). Contractor on record: UNIMASTERS CONGLOMERATION INC. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A

DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.

Region: Region IV-A

No before/after satellite images: DPWH did not publish coordinates, and the location estimated from the project title is only town level, which is not confident enough to image.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱3,700 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-C-17-0000692 · ₱100,000,000 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17DN0166 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF ONE (1) UNIT FOUR (4) STOREY, SIXTEEN (16) CLASSROOMS SCHOOL BUILDING, BAGONG PAGASA ELEMENTARY SCHOOL (SAN JUAN B. FLOODWAY ES), TAYTAY, RIZAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱3,700,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Drainage Canal along Floodway Road Westbank, Rizal
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-17-0000692

₱100,000,000.00 · FY2017

Released to National Electrification Administration (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

50 projects · ₱2.3B total · 0 flags

Other projects by this contractor

No sat.

ROAD WIDENING - PRIMARY ROADS - PALO - CARIGARA - ORMOC ROAD - KO975+061 - KO975+788, KO975+832.20 - KO980+372, KO982+186 - KO983+255, KO940+454 - KO940+895, LEYTE 2ND LD

Region VIII, Region VIII

2018₱165.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASSES ROAD, INCLUDING ROW NRJ DAANG MAHARLIKA, TAGUIBO-MASAO PORT, (CABCABON-BANZA SECTION), BUTUAN CITY, AGUSAN DEL NORTE 1ST LD., BUTUAN CITY, AGUSAN DEL NORTE 1ST LD.

Region XIII, Region XIII

2016₱140.3M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - PALO - CARIGARA - ORMOC RD. - K0953+466 - K0954+288, K0954+299 - K0955+000, K0955+000 - K0955+344, K0955+357 - K0956+233, CARIGARA, LEYTE 2ND LD

Region VIII, Region VIII

2020₱122.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, SAN FRANCISCO (NRJ HUBANG - STA. ANA - SAN ISIDRO) BYPASS ROAD (DAANG MAHARLIKA ALTERNATE ROUTE), INCLUDING ROW AND BRIDGE, SAN FRANCISCO, AGUSAN DEL SUR

Region XIII, Region XIII

2018₱119.8M
Reported complete (DPWH)
No sat.

IMPROVEMENT/WIDENING OF NATIONAL ROADS, DAANG MAHARLIKA (SURIGAO-AGUSAN SECT.), K1197+550-K1199+289.40, K1202+000-K1202+812.46, K1202+911.75-K1203+238, AGUSAN DEL NORTE

Region XIII, Region XIII

2017₱102.3M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF DIKE WITH CONCRETE REVETMENT ALONG PANDANON - MAGALLANES ROAD, AGUSAN DEL NORTE

Agusan del Norte DEO, Region XIII

2020₱96.5M
Reported complete (DPWH)
View all 50 projects →

4. Implementation

Contract Amount

₱44,773,435.20

Progress

Reported complete (DPWH)

Start Date

December 12, 2017

Target End

November 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Cite this record

Love the Philippines. “CONSTRUCTION OF ONE (1) UNIT FOUR (4) STOREY, SIXTEEN (16) CLASSROOMS SCHOOL BUILDING, BAGONG PAGASA ELEMENTARY SCHOOL (SAN JUAN B. FLOODWAY ES), TAYTAY, RIZAL.” Source: DPWH. Data as of October 21, 2026. https://lovethephilippines.com/projects/72e2e446-1883-4ed8-8e0b-70564c3e4946

The official source record is authoritative. An indicator on this site is not a finding of wrongdoing.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)RizalTaytay
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.