Buildings and Facilities19FC0165

CONSTRUCTION OF MULTI-PURPOSE BUILDING MANDAZO ELEMENTARY SCHOOL, BRGY. MANDAZO, BASUD CAMS. NORTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING MANDAZO ELEMENTARY SCHOOL, BRGY. MANDAZO, BASUD CAMS. NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱1,926,241.72. Status: Reported complete (DPWH). Contractor on record: GVENTURES INC. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-19-0018815

₱0.00 · FY2019

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

17 projects · ₱71.1M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), SAN LORENZO RUIZ, CAMARINES NORTE

Camarines Norte DEO, Region V

2022₱9.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTIPURPOSE (SENIOR CITIZENS BUILDING), WITH COVERED COURT BARANGAY GUINACUTAN VINZON, CAMA

Region V, Region V

2024₱9.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 3, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2022₱5.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM(BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, MAMBUNGALON ELEMENTARY SCHOOL, BARANGAY MAMBUNGALON, MERCEDES, CAMAR

Region V, Region V

2023₱4.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BARANGAY MANMUNTAY, BASUD, CAMARINES NORTE, BASUD, CAMAR

Region V, Region V

2025₱4.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT), OLIVA ELEMENTARY SCHOOL, BARANGAY OLIVA, BAS

Region V, Region V

2023₱4.0M
Reported complete (DPWH)
View all 17 projects →

4. Implementation

Contract Amount

₱1,926,241.72

Progress

Reported complete (DPWH)

Start Date

July 8, 2019

Target End

September 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.