Roads24D00197

CONSTRUCTION OF ROAD CONNECTING CARMONA-SILANG DIVERSION ROAD AND SLEX EXIT, PHASE 1, CARMONA CITY, CAVITE

CONSTRUCTION OF ROAD CONNECTING CARMONA-SILANG DIVERSION ROAD AND SLEX EXIT, PHASE 1, CARMONA CITY, CAVITE is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱142,578,745.39. Status: Past target date (DPWH On-Going). Contractor on record: OCTAGON CONCRETE SOLUTIONS INC 34475. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 34475

69 projects · ₱6.7B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM (LP) - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF TACLOBAN AIRPORT PASSENGER TERMINAL BUILDING PHASE 3, TACLOBAN CITY

Region VIII, Region VIII

2024₱964.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONST. OF AIRPORT FACILITY, BUSUANGA AIRPORT, CORON, PALAWAN

Region IV-B, Region IV-B

2024₱400.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPL. SUPPORT PROG.-SUSTAINABLE INFRA PROJS. ALLEVIATING GAPS (SIPAG)-ACCESS RDS. &/OR BRS. FR. THE NAT'L. RDS./S LEAD. TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF R0AD, BRGY. LIYANG, PILAR TO BRGY. BILOLO, ORION, BATAAN (PACKAGE 1)

Region III, Region III

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING OF PUERTO PRINCESA NORTH ROAD FROM TWO (2) LANES TO SIX (6) LANES INCLUDING DRAINAGE K0115+949 TO K0118+000, ROXAS, PALAWAN

Region IV-B, Region IV-B

2018₱162.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (UPSTREAM LEFTSIDE), ABORLAN, PALAWAN

Region IV-B, Region IV-B

2024₱154.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ABORLAN RIVER WATERWAY, PUERTO PRINCESA SOUTH ROAD (UPSTREAM RIGHTIDE), ABORLAN, PALAWAN

Region IV-B, Region IV-B

2024₱147.1M
Past target date (DPWH On-Going)
View all 69 projects →

4. Implementation

Contract Amount

₱142,578,745.39

Progress

Past target date (DPWH On-Going)

Start Date

August 8, 2024

Target End

June 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.