GAA 2025 OO-225ME0080

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NEW LA UNION, MAITUM, SARANGANI PROVINCE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, NEW LA UNION, MAITUM, SARANGANI PROVINCE is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱38,023,383.33. Status: Past target date (DPWH On-Going). Contractor on record: BETTER WORK CONST. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, New La Union, Maitum, Sarangani
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Sarangani DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱38,023,383.33

Progress

Past target date (DPWH On-Going)

Start Date

July 15, 2025

Target End

March 11, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.