Flood Control and Drainage17GJ0076

CONSTRUCTION OF SLOPE PROTECTION AND IMPROVEMENT ALONG ILOILO RIVER INCLUDING FOOTBRIDGE, LEFT BANK (B.S. AQUINO JR. AVENUE TO JALANDONI BRIDGE), ILOILO CITY

CONSTRUCTION OF SLOPE PROTECTION AND IMPROVEMENT ALONG ILOILO RIVER INCLUDING FOOTBRIDGE, LEFT BANK (B.S. AQUINO JR. AVENUE TO JALANDONI BRIDGE), ILOILO CITY is a DPWH-tracked public work in Iloilo City DEO, Region VI. Reported contract value: ₱57,076,624.00. Status: Reported complete (DPWH). Contractor on record: ROPRIM CONST CORP FORMERLY ROPRIM CONST. Figures trace to dpwh.

Iloilo City DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Guimbal River Revetment and Flood Control Structures, Guimbal, Iloilo
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-17-0025617

₱2,472,071.00 · FY2017

Released to Regional Office - Proper (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱57,076,624.00

Progress

Reported complete (DPWH)

Start Date

June 13, 2017

Target End

October 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.