Buildings and Facilities24HC0125

REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY BONBON, CLARIN, BOHOL

REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY BONBON, CLARIN, BOHOL is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱4,875,750.00. Status: Reported complete (DPWH). Contractor on record: RL EARTH HAULING. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ubay Flood Control Structure, Barangay Bongbong - Barangay San Pascual, Ubay, Bohol
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bohol 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

22 projects · ₱322.8M total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - THE PRES. CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0233+007 - K0233+350, K0234+375 - K0234+949

Bohol 3rd DEO, Region VII

2025₱30.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF JCT. (TER) GUINDULMAN - CA

Bohol 3rd DEO, Region VII

2022₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, JCT. (LIR), MAHAYAG

Bohol 2nd DEO, Region VII

2023₱29.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS TAGBILARAN EAST RD (TAGBILARAN-JAGNA) - K0177 + 583 - K0177 +

Bohol 3rd DEO, Region VII

2024₱29.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/ REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES -LOCAL ROADS - CONCRETING OF ROAD, BAGUMBAYAN-BUGHO, LOBOC, BOHOL STA.0+000 - STA.0+523.99; STA.0+561.42 - STA.1+223.2

Bohol 3rd DEO, Region VII

2021₱25.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (CONCRETING) OF ROAD AT BARANGAY POBLACION IBABAO TO BARA

Bohol 3rd DEO, Region VII

2023₱24.7M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱4,875,750.00

Progress

Reported complete (DPWH)

Start Date

September 9, 2024

Target End

April 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.