Bridges18GA0070

WIDENING OF PUPOS BRIDGE (B00289PN) ALONG AKLAN EAST ROAD INCLUDING ROW, ALTAVAS, AKLAN

WIDENING OF PUPOS BRIDGE (B00289PN) ALONG AKLAN EAST ROAD INCLUDING ROW, ALTAVAS, AKLAN is a DPWH-tracked public work in Aklan DEO, Region VI. Reported contract value: ₱9,029,865.73. Status: Reported complete (DPWH). Contractor on record: SDB STEELSTRUCT BUILDERS ENT. Figures trace to dpwh.

Aklan DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of River Control (Revetment Wall) along Aklan River including other structures/facilities, Lezo, Aklan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-18-0025401

₱0.00 · FY2018

Released to Division of Aklan (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,029,865.73

Progress

Reported complete (DPWH)

Start Date

April 18, 2018

Target End

November 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.