Buildings and Facilities25OB0452

CONSTRUCTION OF MULTI-PURPOSE BUILDING (RFU-NCR MEGA LABORATORY BUILDING), 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE VI)

CONSTRUCTION OF MULTI-PURPOSE BUILDING (RFU-NCR MEGA LABORATORY BUILDING), 1ST QUADRANT OF CAMP BAGONG DIWA ALONG GEN. SANTOS AVE., BICUTAN, TAGUIG CITY (PHASE VI) is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱141,782,392.82. Status: Past target date (DPWH On-Going). Contractor on record: A M ORETA. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱23,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structure along Ermitaño Creek, Barangay Addition Hills, San Juan City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Metro Manila 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

28 projects · ₱2.5B total · 0 flags

Other projects by this contractor

View all 28 projects →

4. Implementation

Contract Amount

₱141,782,392.82

Progress

Past target date (DPWH On-Going)

Start Date

June 5, 2025

Target End

May 30, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.