Bridges23E00014

BRIDGE PROGRAM WIDENING OF PERMANENT BRIDGES LUMINTAO BR. (B00084MR) ALONG MINDORO WEST COASTAL ROAD (COMPLETION), OCCIDENTAL MINDORO

BRIDGE PROGRAM WIDENING OF PERMANENT BRIDGES LUMINTAO BR. (B00084MR) ALONG MINDORO WEST COASTAL ROAD (COMPLETION), OCCIDENTAL MINDORO is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱289,497,735.42. Status: Reported complete (DPWH). Contractor on record: PLERM CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

39 projects · ₱3.8B total · 0 flags

4. Implementation

Contract Amount

₱289,497,735.42

Progress

Reported complete (DPWH)

Start Date

February 11, 2023

Target End

March 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.