Roads17IC0060

NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-OTHER PRIMARY ALONG PALO-CARIGARA-ORMOC ROAD, K0916+(-107) - K0916+795, K0916+809 - K0916+(-107), K0926+407 - K0927+221, K0927+233 - K0928+673, PALO-ALANGALANG, LEYTE

NETWORK DEVELOPMENT-IMPROVEMENT/WIDENING OF NATIONAL ROADS-OTHER PRIMARY ALONG PALO-CARIGARA-ORMOC ROAD, K0916+(-107) - K0916+795, K0916+809 - K0916+(-107), K0926+407 - K0927+221, K0927+233 - K0928+673, PALO-ALANGALANG, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱108,138,063.98. Status: Reported complete (DPWH). Contractor on record: TRIBU DESIGN & CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Bangon River, Palo, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0005022

₱10,000,000.00 · FY2017

Released to Camarines Sur 3rd Re District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱108,138,063.98

Progress

Reported complete (DPWH)

Start Date

July 12, 2017

Target End

April 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.