Flood Control and Drainage16BJ0023

CONSTRUCTION OF CALITLITAN FLOOD CONTROL ALONG DAANG MAHARLIKA (PHASE II), CALITLITAN SECTION, ARITAO, NUEVA VIZCAYA

CONSTRUCTION OF CALITLITAN FLOOD CONTROL ALONG DAANG MAHARLIKA (PHASE II), CALITLITAN SECTION, ARITAO, NUEVA VIZCAYA is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱18,595,552.32. Status: Reported complete (DPWH). Contractor on record: TRIBU DESIGN & CONST. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 98%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Calitlitan Flood Control along Daang Maharlika (Phase II), Calitlitan Section, Aritao, Nueva Vizcaya
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-16-0037974

₱485,000.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱18,595,552.32

Progress

Reported complete (DPWH)

Start Date

January 26, 2016

Target End

May 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.