Roads18BD0080

NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, PRIMARY ROADS, KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION), K0438+010 - K0441+576, K0441+600 - K0443+765

NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, PRIMARY ROADS, KALINGA-CAGAYAN ROAD (CALANAN-ENRILE SECTION), K0438+010 - K0441+576, K0441+600 - K0443+765 is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱70,063,815.05. Status: Reported complete (DPWH). Contractor on record: JTA BUILDERS. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System (Downstream), Natappian, Solana, Cagayan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-18-0002813

₱6,117,152.00 · FY2018

Released to Regional Office - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

112 projects · ₱2.0B total · 0 flags

Other projects by this contractor

View all 112 projects →

4. Implementation

Contract Amount

₱70,063,815.05

Progress

Reported complete (DPWH)

Start Date

April 30, 2018

Target End

March 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.