Roads16HD0088

REHAB/RECONST/UPGRDG OF NATL RD INCLDG DRAINAGE (HDM-4) ALONG AYDPH, TABUELAN & SAN REMEGIO

REHAB/RECONST/UPGRDG OF NATL RD INCLDG DRAINAGE (HDM-4) ALONG AYDPH, TABUELAN & SAN REMEGIO is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱23,674,738.43. Status: Reported complete (DPWH). Contractor on record: CYJE FIRST BUILDERS CONST CORP FORMERLY: FIRST BUILDERS AND DEVELOPERS. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Completion of Alegria river flood control dike, Alegria, Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0011285

₱113,011.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱23,674,738.43

Progress

Reported complete (DPWH)

Start Date

March 6, 2017

Target End

October 11, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.