Roads18CM0076

ROAD WIDENING - SECONDARY ROADS, OLONGAPO-BUGALLON ROAD, K0148+500 - K0148+747, K0148+767.2 - K0148+940, K0149+002 - K0150+090, SAN MARCELINO, ZAMBALES

ROAD WIDENING - SECONDARY ROADS, OLONGAPO-BUGALLON ROAD, K0148+500 - K0148+747, K0148+767.2 - K0148+940, K0149+002 - K0150+090, SAN MARCELINO, ZAMBALES is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱93,325,113.12. Status: Reported complete (DPWH). Contractor on record: REPOLMAN CONST CORP FORMERLY: REPOLMAN CONST. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Camachile River, San Marcelino, Zambales
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0022785

₱0.00 · FY2018

Released to Division of Zambales (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

121 projects · ₱4.4B total · 0 flags

4. Implementation

Contract Amount

₱93,325,113.12

Progress

Reported complete (DPWH)

Start Date

June 22, 2018

Target End

March 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.