Flood Control and Drainage16AB0043

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, SABO/FLOOD CONTROL PROJECTS ALONG LAOAG RIVER BASIN & PRINCIPAL RIVERS/TRIBUTARIES - CONTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN JULIAN, SITIO BATO, BADOC, ILOCOS NORTE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, SABO/FLOOD CONTROL PROJECTS ALONG LAOAG RIVER BASIN & PRINCIPAL RIVERS/TRIBUTARIES - CONTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN JULIAN, SITIO BATO, BADOC, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱7,714,535.97. Status: Reported complete (DPWH). Contractor on record: BADOC BUILDERS. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2016 · ₱8,000

    Probable match · score 0.92

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-B-16-0038832 · ₱3,395,952 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 16AB0043 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-02-16 → 2025-04-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Ilocos Norte

Based on the coordinates published with the DPWH record and NOAH file IlocosNorte.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, SABO/FLOOD CONTROL PROJECTS ALONG LAOAG RIVER BASIN & PRINCIPAL RIVERS/TRIBUTARIES - CONTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN JULIAN, SITIO BATO, BADOC, ILOCOS NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Sabo/Flood Control Projects along Laoag River Basin and Principal Rivers/Tributaries - Construction of Flood Control Structure, Brgy San Julian, Sitio Batu, Badoc, Ilocos Norte 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-16-0038832

₱3,395,952.00 · FY2016

Released to Central Off (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

117 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱7,714,535.97

Progress

Reported complete (DPWH)

Start Date

March 16, 2016

Target End

August 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region I (Ilocos Region)Ilocos NorteBadocBato
Storms whose wind field reached it
Peilou 2026Noul 2026Fung-Wong 2025Matmo 2025Ragasa 2025
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.