Flood Control and Drainage16AB0043

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, SABO/FLOOD CONTROL PROJECTS ALONG LAOAG RIVER BASIN & PRINCIPAL RIVERS/TRIBUTARIES - CONTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN JULIAN, SITIO BATO, BADOC, ILOCOS NORTE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, SABO/FLOOD CONTROL PROJECTS ALONG LAOAG RIVER BASIN & PRINCIPAL RIVERS/TRIBUTARIES - CONTRUCTION OF FLOOD CONTROL STRUCTURE, BRGY. SAN JULIAN, SITIO BATO, BADOC, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱7,714,535.97. Status: Reported complete (DPWH). Contractor on record: BADOC BUILDERS. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Sabo/Flood Control Projects along Laoag River Basin and Principal Rivers/Tributaries - Construction of Flood Control Structure, Brgy San Julian, Sitio Batu, Badoc, Ilocos Norte 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-16-0038832

₱3,395,952.00 · FY2016

Released to Central Off (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

117 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱7,714,535.97

Progress

Reported complete (DPWH)

Start Date

March 16, 2016

Target End

August 18, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.