Bridges18GI0026

REHABILITATION/MAJOR REPAIR OF BRIDGE - TALAUGIS BR. (B00475PN) ALONG ILOILO CITY - LEGANES - DUMANGAS COASTAL RD.

REHABILITATION/MAJOR REPAIR OF BRIDGE - TALAUGIS BR. (B00475PN) ALONG ILOILO CITY - LEGANES - DUMANGAS COASTAL RD. is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱30,883,488.54. Status: Reported complete (DPWH). Contractor on record: EC STRUCTURAL COMPOSITES INC. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection/Bank Improvement along Iloilo River, Right Bank (From Jalandoni Bridge to Forbes Bridge), Iloilo City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-18-0007875

₱79,883.00 · FY2018

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱30,883,488.54

Progress

Reported complete (DPWH)

Start Date

February 27, 2018

Target End

September 4, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.