Construction of Flood Mitigation Structure24ME0017

Construction of Pangi Left CIS Protection Works, Maitum, Sarangani

Construction of Pangi Left CIS Protection Works, Maitum, Sarangani is a DPWH-tracked public work in MAITUM (SARANGANI), SARANGANI, Region XII. Reported contract value: ₱14,514,426.28. Status: Reported complete (DPWH). Contractor on record: XIANN THIRDREI BUILDERS. Figures trace to sumbong.

MAITUM (SARANGANI), SARANGANI, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ladol Flood Control, Alabel, Sarangani
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0007653

₱1,825,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0007843

₱168,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱14,514,426.28

Progress

Reported complete (DPWH)

Start Date

April 9, 2024

Target End

November 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.