Roads19EH0048

CONSTRUCTION OF PATOO - MAINIT - BATIANO ROADK000 + 000.00 - K000 + 400.00, ODIONGAN, ROMBLON

CONSTRUCTION OF PATOO - MAINIT - BATIANO ROADK000 + 000.00 - K000 + 400.00, ODIONGAN, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱4,899,999.18. Status: Reported complete (DPWH). Contractor on record: TWIN DRAGON CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,899,999.18

Progress

Reported complete (DPWH)

Start Date

July 1, 2019

Target End

August 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.