GAA 2016 MFO-116PL0002

REPLACEMENT OF BRIDGES FROM TEMPORARY TO PERMANENT OF BULO BRIDGE 1 (B01338LZ) ALONG BULO NATIONAL ROAD (AGBANNAWAG-BULO-CALLAGDAO SECTION)

REPLACEMENT OF BRIDGES FROM TEMPORARY TO PERMANENT OF BULO BRIDGE 1 (B01338LZ) ALONG BULO NATIONAL ROAD (AGBANNAWAG-BULO-CALLAGDAO SECTION) is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱24,308,967.82. Status: Reported complete (DPWH). Contractor on record: OMENGAN CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0018250

₱291,777.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

62 projects · ₱4.2B total · 0 flags

Other projects by this contractor

No sat.

CONST/IMPVT OF ACCESS RDS LEADING TO AIRPORTS, SEAPORTS, AND DTD, CUDOG-MUNGAYANG-KIANGAN ROAD LEADING TO AMBUAYA LAKE, YAMASHITA SHRINE, AND KIYANGAN SETTLEMENT, KIANGAN AND LAGAWE, IFUGAO (INCLUDING CONSTRUCTION OF BRIDGES)

Cordillera Administrative Region, Cordillera Administrative Region

2016₱188.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONST. OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, ASIN - NANGALISANJCT. - BAYABAS - MONGLO JCT. (SECTION 1)

Cordillera Administrative Region, Cordillera Administrative Region

2020₱173.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION AND MAINTAINANCE OF BRIDGE ALONG NATIONAL ROADS CONSTRUCTION OF NEW PERMANENT BRIDGE TABBAYAGAN BRIDGE ALONG APAYAO-ILOCOS NORTE ROAD

Cordillera Administrative Region, Cordillera Administrative Region

2017₱154.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ASSET PRESERVATION - CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MANUEL S. AGYAO BOULEVARD-K0499 + 908 -K0500 + 467, K0508 + 130 - K0509 + 351

Lower Kalinga DEO, Cordillera Administrative Region

2024₱152.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT AND EMBANKMENT OF DIKE AND CHANNELING ALONG CHICO RIVER, TABUK CITY, KALINGA

Cordillera Administrative Region, Cordillera Administrative Region

2023₱144.8M
Past target date (DPWH On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) APAYAO - ILOCOS NORTE ROAD, K0616+000 - K0619+750

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.7M
Reported complete (DPWH)
View all 62 projects →

4. Implementation

Contract Amount

₱24,308,967.82

Progress

Reported complete (DPWH)

Start Date

April 11, 2016

Target End

June 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.