Roads24F00030

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0305+406-K0305+880, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0305+406-K0305+880, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱36,497,240.00. Status: Past target date (DPWH On-Going). Contractor on record: E GARCIA CONST CORP FOR E GARCIA CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱36,497,240 · E.GARCIA CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    76% reported · imagery 2017-08-08 → 2025-04-17

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (widening)

₱76,998,397 per km= 1.8x the Region V median (n=215)

Contract cost ₱36,497,240 ÷ 0.474 km read from the DPWH title (“K0305+406-K0305+880”; K-post / station range length). National percentile: 96. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0305+406-K0305+880, LABO, CAMARINES NORTE (1ST LEGISLATIVE DISTRICT

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24F00030

₱36,497,240.00 · E.GARCIA CONSTRUCTION

Award / contract ref: 24F00030

Contractor

B

115 projects · ₱7.1B total · 3 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, ROLANDO A. ANDAYA HIGHWAY, CAMARINES SUR, K0282+(-186)-K0282+(-181), K0282+160-K0282+245, K0282+3

Region V, Region V

2019₱240.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER FLOOD CONTROL STRUCTURE (DOGONGAN SECTION-PACKAGE

Region V, Region V

2024₱238.7M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF DAET RIVER FLOOD CONTROL STRUCTURE (DOGONGAN SECTION-PACKAGE

Region V, Region V

2024₱236.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, DAET RIVER, BARANGAY BIBIRAO, DAE

Region V, Region V

2025₱235.2M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. SAN JOSE, STA. 000+000-STA. 000+371.65, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱231.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. MELGAR A, STA. 000+000-STA. 000+463.95, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱230.7M
Past target date (DPWH On-Going)
View all 115 projects →

4. Implementation

Contract Amount

₱36,497,240.00

Progress

Past target date (DPWH On-Going)

Start Date

April 19, 2024

Target End

October 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)Camarines NorteLaboMacogon
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.