Roads24DO0020

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY SAN JOSE, RODRIGUEZ, RIZAL

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY SAN JOSE, RODRIGUEZ, RIZAL is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱28,510,480.08. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: GLJ CONST. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in Barangay Ampid - 1, San Mateo, Rizal
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Rizal 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

7 projects · ₱132.3M total · 0 flags

Other projects by this contractor

View all 7 projects →

4. Implementation

Contract Amount

₱28,510,480.08

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 7, 2024

Target End

May 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.