Roads23EA0079

CONCRETING OF BRGY. MAGAPUA TO BRGY. MALAYAK FMR PHASE II, BRGY. MAGAPUA AND BRGY. MALAYAK, MOGPOG, MARINDUQUE

CONCRETING OF BRGY. MAGAPUA TO BRGY. MALAYAK FMR PHASE II, BRGY. MAGAPUA AND BRGY. MALAYAK, MOGPOG, MARINDUQUE is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱46,763,297.85. Status: Reported complete (DPWH). Contractor on record: M C J VALENZUELA CONST ENT 40623. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Banto, Mogpog, Marinduque
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Marinduque DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 40623

32 projects · ₱846.1M total · 0 flags

Other projects by this contractor

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION/REHABILITATION OF FLOOD CONTROL PROJECT IN CALAGUIMAN RIVER PHASE 2BSAMAL, BATAAN

Bataan 1st DEO, Region III

2021₱96.5M
Reported complete (DPWH)

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COLO RIVER, BAMBAN SECTION, PHASE III-DM, HERMOSA, BATAAN

Bataan 1st DEO, Region III

2024₱96.5M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG ALMACEN RIVER CUT-OFF CHANNEL, PHASE IV-DMC, HERMOSA, BATAAN

Bataan 1st DEO, Region III

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG ORANI CHANNEL, PANTALAN LUMA, PHASE IV-DMC, ORANI, BATAAN

Bataan 1st DEO, Region III

2024₱94.1M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MABIGA RIVER, TRIBUTARY TO COLO RIVER, PHASE III-DM, HERMOSA, BATAAN

Bataan 1st DEO, Region III

2024₱72.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS -CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COLO RIVER (PHASE III-DM), PALIHAN SECTION, HERMOSA, BATAAN

Bataan 1st DEO, Region III

2024₱72.4M
Reported complete (100% progress, DPWH status On-Going)
View all 32 projects →

4. Implementation

Contract Amount

₱46,763,297.85

Progress

Reported complete (DPWH)

Start Date

March 28, 2023

Target End

May 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.